House Construction Process In Nepal and Costing


Ref. No:
Master Plan Design and Drawing
Name of Project :- Preparation of Master Plan ,Drawing, Design , Structure Design , Exterior Modeling of Building blocks
Project Summary
SN. Particular Amount Result/ Deliverables
1 Site Survey with Total Station , Surveyor & Assistant team with logistics of team to Dhading (Site Field Visit & Inspection) 32,000.00 Surveyed Map (1:100 Scale)
2 Detailed Concept Planning of Building Block with Placement , Design and Development of Concept in Drawing (2D Autocad) for Real Construction Work by Concept Planner Expert team ( Construction Team , Engineer, Architect) Master Plan Drawing with Beautiful Project placing all blocks in right position and land suitable design and structures with Engineering Safety and Space utilize focused
3 Detailed layout and plan of Septic Tank , Soak Pit ,Water Filter 25,000.00 Drain and Water Filter Placement Layout, Plumbing, Soak Pit Layout Map
4 Master Plan Drawing & Design of Building block ,1 Sport Ground , 1 Vegetable Garden , Solar Panel for Hot Water & Energy for Light , Water Filter System ,2 Ropani Land 75,200.00 Master Plan Including all Blocks in A1 Size Paper
5 Architectural Drawing of 6 Bedrooms Hostel Building (20 sq. m number 6) 38,736.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
6 Architectural Drawing of 1 Dinning Hall 20sq.m 9,684.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
7 Architectural Drawing of Reading Hall 40 Sqm. 19,368.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
8 Architectural Drawing of Meeting Hall 20 sq. m 7,532.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
9 1 Warden Family House Drawing 50 Sqm. 17,216.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
10 2 common bathrooms plus common toilet and hand washing facilities for 35 girls 14,526.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
11 Structural Column Plan , Layout , Truss Details , of All Building Blocks 190,500.00 structural column plan , truss details ,section x-x of Each Block in (A-2 Size), Working Drawing of Building Blocks in A-2
12 Foundation Footing Details & Working Drawing of All Building Blocks 45000.00 Footing Details and Working Drawing of Building in (A-2 ) Size Paper
13 Exterior Model of Building , Landscaping model & Exterior Visualization and Walk through of Complete project Not Required During meeting discussion suggested not required.
14 Bill of Quantity Preparation For Building Blocks 27,000.00 BOQ with Cost For Construction &Material Specification of Structure,Roofing,Wall,Door/Window in details
15 Structure Analysis Report of the Hostel Building >1000 Sqft. 32,550.00 structural report with data analysis and structure recommendations)
16 Electrical & Lighting Placement Drawing 32000.00 Light , Power Socket Drawing in A-2 Size
17 Solar System Installation Modelling and Plan with Details Drawings 30,000.00 Solar Panel Installation Drawing and System Supply Connection Drawing
Subtotal 5961312.00
Total With VAT 13% & 77520.56
Total 673882.56
Note :- Phase #1
Arch. Architectural
COST ESTIMATE FOR Quality Assurance
COST ESTIMATE FOR Quality Assurance
HIRING CONSULTING FIRMS TO CONDUCT FOR Quality Monitoring & Technical Reporting’s During Construction Work and Verifying Work Execution of Prefab Hostel Building with other Necessary Block Project.
S.N Description Person Unit Hr. Rate Total Remark
A Salary of Personnel
2 Architectural Engineer with Construction Supervision 1 14 7500 105,000.00
3 Civil Engineer with Supervision 1 5 5500 27,500.00 .
4 Technical /Structure Engineer Supervision 1 4 16500 66,000.00
Tank, Soak pit, Plumbing , Landscape Supervision 1 5 3500 17,500.00
5 Interior Design, Furniture, Kitchen Designer, Hall Design Consultant 1 5 21500 107500.00
6 ,Electrical Engineer , Sanitary & Waste Manage Expert 1 5 21500 107500.00
A Sub Total 431,000.00
B Miscellaneous expenses
Communication cost 7000.00
Drafting/ reports 20000.00
Equipment’s, vehicles, computers , Software , Analysis 20000.00
Sub Total 47000.00
Grand Total 478000.00
VAT @13% of G 62140.00
Total (G+H) 540,140.00
Building design process
Content
1. Site Survey- Map, Photo, Trace map , Google Map
2. The Concept Plan of the overall project by design team
3. Establishing the need & Requirements with eco-friendly focus.
4. Feasibility Study & Site Survey for the Given Requirement of Building
5. Selection of designers , Structural Engineers as per the job schedules,
6. Drawing and Detailing of Concept design & Planner in AutoCAD and other Software
7. Detailed design –Architectural ,Structural Drawing
8. Production information of Landscape, Ground, Boundary, Building, Draining, Water, Plumbing Works for Construction on-site.
9. Building Model & Structural Design & development with Walk Through
10. Bill of Quantity & Material Specification –
11. Final Cost Estimate Preparation for Construction of Project as per drawing & Design.
12. BID Documents Preparation( If Required)
13. Conclusion ;Find out more & Better Improve
Building’s Construction process
Note: Final Costing and BOQ will be after Preparation of Detailed Project Report( Master Plan, Architectural Drawing , Structural Drawing , Opening Schedules, Foundation Details )
1. Make Booklet Copy with All detailed drawings, master plan, photos.
2. Bid Documents and Get EOI -Comparison
3. Select the Expert and Competitive Firm for Project Execution.
4. Establishing the Scope of Work with the specified Cost for given Work.
5. MoU between Clients and Contractors
6. Start off Project Work with Civil Works,
7. Followed by Foundation, Structure, Wall, Roofing, False Ceiling, Doors/Window Installation / Electrical and Plumbing Works.
8. Quality Assurance by Expert on consulting the work on site specially focused on Architectural Design and Structural Works, Interior Designing, Electrical, Landscape Works.
9. Painting and Finishing Work of Building
10. Production of Futsal, Play Ground, Pavement, Drain – Soak pit, water tank management for Construction on-site.
11. Building Model & Real Construction Comparison and verify and work out best to make everything smooth and fine.
12. Project Summary Reporting and Handover –
13. Find out more & Better Improve
Quality Assurance Process
1. Site Visit and Verify the construction work as per all detailed drawings, master plan, model and photos.
2. Prepare Report and Recommend Contractor for the Work Punch list.
3. Measure, plan and guide for water tank, drain, electrical wiring works.
4. Verifying the Scope of Work and make Clarity between Client and Contractor by the Report of Civil Engineer for given Work.
5. MoU between Clients and Contractors
6. Quality Assurance by Expert on consulting the work on site specially focused on Architectural Design and Structural Works, Interior Designing, Electrical, Landscape Works.
7. Assure Building Safety, Usability and Functionality
8. Guide Worker for Play Ground, Pavement, Drain – Soak pit, water tank management for Construction on-site by Engineer/ Team Leader.
9. Building Model & Real Construction Comparison and verify and work out best to make everything smooth and fine.
10. Project Summary Reporting and Handover –
11. Find out more & Better Improve
Abstract of Cost
Project: Estimate cost of Hostel Building and Prefab Building Block at Dhading , Nepal
Type of work: Construction of Prefab Building Block for Hostel with
Complete works including Boundary wall
Date: January 14 2020
S.n Description of work L, m W,m H,m Area (Sqm. /cum.)
Total Price Deliverables
I Construction of Prefab 6 Bedrooms for 35 Girls Each 20 Sqm.) 1 15.700 7.65 2.75 120 4200071.85 6 Rooms with Door/Window, Light Non-Furnished )
II Construction of Prefab Dinning Hall 1 6 3.25 2.75 20 891735 Hall Room Unfurnished
III Construction of Prefab Kitchen Hall 1 6 3.25 2.75 20 723879 Kitchen with modular Cabinets & Counter Top
IV Construction of Prefab Hall for Reading /TV/ 1 10 4.00 2.75 40 1398800 Hall Room with Unfurnished
V Construction of Prefab Meeting Hall 1 8 3.25 2.75 26 965172 Meeting Hall Unfurnished
VI Construction of Prefab Warden Family House 1 12 4.00 2.75 48 1781856 Family House with Non Furnished
VII Construction of Prefab Common toilet/bathrooms 1 8 3.25 2.75 26 1077076 Toilets with Commode, Tiles, Shower, tap
VIII Construction of Soak pit for Waste and Drain manage 4 2 2.00 1.5 24
cu.m 925000
IX Construction of Water Tank 1 4 2.00 2 12 cu.m 1680000
Sub-total (A) NPR 13,643,589.85
1.2 Installation of Green Solar Plant for Energy Source 2 KW 1 3.00 4.00 NPR 725,300.00 2 Kw solar and 5 lights & System
1.3 Futsal Playground of Size 40 feet x70 fet 1 40.00 10.00 NPR 925,320.00 Futsal Playground
1.4 Compound Work with Metal Pipe & CGI Fencing ( For 2 Ropani Land 1 190 m NPR 1,533,300.00 Metal Fencing with CGI Sheet Cover
1.5 Installation of Water Filter System 1
NPR 455,500.00 Water Filter of 200 liter.
1.6 Installation of Pavement in Ground for 2 Ropani Land (Assumed) 1 100 Sqm NPR 1,150,000.00 Hexagon Pavement in Ground
1.7 Installation of Water Heating Solar for Hot Water Supply 200 l NPR 325,000.00 200l water heating
1.8 Installation of Solar System for Cooking
3 KW( Instead of Bio-Gas) 1 NPR 1,125,000.00 Solar System for Cooking
1.9
Sub-total(B) NPR 6,239,420.00
Total(A+B) NPR 19,883,009.00
VAT 13% NPR 2,584,791.28
Scope of Work Grand Total NPR 22,467,801.13
1 Structure Metal , Prefab Wall , Doors/Window , Roofing False Ceiling ,Painting with turn-key solution
2 25-30 % Advance during MOU
3
Submitted by:
Checked by:
Approved by:
Project Timeline
Address: Dhading
Project :
Starting Date: March First Week
Completion Date:
Project Duration: 5 Months
S.N Works Duration (weeks) Time Period (Week)
3-Mar 25-Mar 5
Apr. 2
May 20
May 2-Jun 25-Jun 2-July 3-
Aug
1 30% Design and Layout 3
2 Site Visit and Custom Fabrication of structure for Project 4
Material for structure and core part delivery 2
3 Structural Metal Frame Installation 3
4 45% Roof Truss and Covering 2
5 Gutter and Flooring PCC 1
6 Ceiling 2
7 Wall Panel installation 3
8 25% Wall Framing Window and Door 2
9 Ground Pavement & Boundary 3
10 Electrification 2
11 Coloring 2
Total Duration : Approx. 5 months including Building Works, Boundary Wall , Ground Pavement
Ref. No:
Master Plan Design and Drawing
Name of Project :- Preparation of Master Plan ,Drawing, Design , Structure Design , Exterior Modeling of Building blocks
Project Summary
SN. Particular Amount Result/ Deliverables
1 Site Survey with Total Station , Surveyor & Assistant team with logistics of team to Dhading (Site Field Visit & Inspection) 32,000.00 Surveyed Map (1:100 Scale)
2 Detailed Concept Planning of Building Block with Placement , Design and Development of Concept in Drawing (2D Autocad) for Real Construction Work by Concept Planner Expert team ( Construction Team , Engineer, Architect) Master Plan Drawing with Beautiful Project placing all blocks in right position and land suitable design and structures with Engineering Safety and Space utilize focused
3 Detailed layout and plan of Septic Tank , Soak Pit ,Water Filter 25,000.00 Drain and Water Filter Placement Layout, Plumbing, Soak Pit Layout Map
4 Master Plan Drawing & Design of Building block ,1 Sport Ground , 1 Vegetable Garden , Solar Panel for Hot Water & Energy for Light , Water Filter System ,2 Ropani Land 75,200.00 Master Plan Including all Blocks in A1 Size Paper
5 Architectural Drawing of 6 Bedrooms Hostel Building (20 sq. m number 6) 38,736.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
6 Architectural Drawing of 1 Dinning Hall 20sq.m 9,684.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
7 Architectural Drawing of Reading Hall 40 Sqm. 19,368.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
8 Architectural Drawing of Meeting Hall 20 sq. m 7,532.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
9 1 Warden Family House Drawing 50 Sqm. 17,216.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
10 2 common bathrooms plus common toilet and hand washing facilities for 35 girls 14,526.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
11 Structural Column Plan , Layout , Truss Details , of All Building Blocks 190,500.00 structural column plan , truss details ,section x-x of Each Block in (A-2 Size), Working Drawing of Building Blocks in A-2
12 Foundation Footing Details & Working Drawing of All Building Blocks 45000.00 Footing Details and Working Drawing of Building in (A-2 ) Size Paper
13 Exterior Model of Building , Landscaping model & Exterior Visualization and Walk through of Complete project Not Required During meeting discussion suggested not required.
14 Bill of Quantity Preparation For Building Blocks 27,000.00 BOQ with Cost For Construction &Material Specification of Structure,Roofing,Wall,Door/Window in details
15 Structure Analysis Report of the Hostel Building >1000 Sqft. 32,550.00 structural report with data analysis and structure recommendations)
16 Electrical & Lighting Placement Drawing 32000.00 Light , Power Socket Drawing in A-2 Size
17 Solar System Installation Modelling and Plan with Details Drawings 30,000.00 Solar Panel Installation Drawing and System Supply Connection Drawing
Subtotal 5961312.00
Total With VAT 13% & 77520.56
Total 673882.56
Note :- Phase #1
Arch. Architectural
COST ESTIMATE FOR Quality Assurance
COST ESTIMATE FOR Quality Assurance
HIRING CONSULTING FIRMS TO CONDUCT FOR Quality Monitoring & Technical Reporting’s During Construction Work and Verifying Work Execution of Prefab Hostel Building with other Necessary Block Project.
S.N Description Person Unit Hr. Rate Total Remark
A Salary of Personnel
2 Architectural Engineer with Construction Supervision 1 14 7500 105,000.00
3 Civil Engineer with Supervision 1 5 5500 27,500.00 .
4 Technical /Structure Engineer Supervision 1 4 16500 66,000.00
Tank, Soak pit, Plumbing , Landscape Supervision 1 5 3500 17,500.00
5 Interior Design, Furniture, Kitchen Designer, Hall Design Consultant 1 5 21500 107500.00
6 ,Electrical Engineer , Sanitary & Waste Manage Expert 1 5 21500 107500.00
A Sub Total 431,000.00
B Miscellaneous expenses
Communication cost 7000.00
Drafting/ reports 20000.00
Equipment’s, vehicles, computers , Software , Analysis 20000.00
Sub Total 47000.00
Grand Total 478000.00
VAT @13% of G 62140.00
Total (G+H) 540,140.00
Building design process
Content
1. Site Survey- Map, Photo, Trace map , Google Map
2. The Concept Plan of the overall project by design team
3. Establishing the need & Requirements with eco-friendly focus.
4. Feasibility Study & Site Survey for the Given Requirement of Building
5. Selection of designers , Structural Engineers as per the job schedules,
6. Drawing and Detailing of Concept design & Planner in AutoCAD and other Software
7. Detailed design –Architectural ,Structural Drawing
8. Production information of Landscape, Ground, Boundary, Building, Draining, Water, Plumbing Works for Construction on-site.
9. Building Model & Structural Design & development with Walk Through
10. Bill of Quantity & Material Specification –
11. Final Cost Estimate Preparation for Construction of Project as per drawing & Design.
12. BID Documents Preparation( If Required)
13. Conclusion ;Find out more & Better Improve
Building’s Construction process
Note: Final Costing and BOQ will be after Preparation of Detailed Project Report( Master Plan, Architectural Drawing , Structural Drawing , Opening Schedules, Foundation Details )
1. Make Booklet Copy with All detailed drawings, master plan, photos.
2. Bid Documents and Get EOI -Comparison
3. Select the Expert and Competitive Firm for Project Execution.
4. Establishing the Scope of Work with the specified Cost for given Work.
5. MoU between Clients and Contractors
6. Start off Project Work with Civil Works,
7. Followed by Foundation, Structure, Wall, Roofing, False Ceiling, Doors/Window Installation / Electrical and Plumbing Works.
8. Quality Assurance by Expert on consulting the work on site specially focused on Architectural Design and Structural Works, Interior Designing, Electrical, Landscape Works.
9. Painting and Finishing Work of Building
10. Production of Futsal, Play Ground, Pavement, Drain – Soak pit, water tank management for Construction on-site.
11. Building Model & Real Construction Comparison and verify and work out best to make everything smooth and fine.
12. Project Summary Reporting and Handover –
13. Find out more & Better Improve
Quality Assurance Process
1. Site Visit and Verify the construction work as per all detailed drawings, master plan, model and photos.
2. Prepare Report and Recommend Contractor for the Work Punch list.
3. Measure, plan and guide for water tank, drain, electrical wiring works.
4. Verifying the Scope of Work and make Clarity between Client and Contractor by the Report of Civil Engineer for given Work.
5. MoU between Clients and Contractors
6. Quality Assurance by Expert on consulting the work on site specially focused on Architectural Design and Structural Works, Interior Designing, Electrical, Landscape Works.
7. Assure Building Safety, Usability and Functionality
8. Guide Worker for Play Ground, Pavement, Drain – Soak pit, water tank management for Construction on-site by Engineer/ Team Leader.
9. Building Model & Real Construction Comparison and verify and work out best to make everything smooth and fine.
10. Project Summary Reporting and Handover –
11. Find out more & Better Improve
Abstract of Cost
Project: Estimate cost of Hostel Building and Prefab Building Block at Dhading , Nepal
Type of work: Construction of Prefab Building Block for Hostel with
Complete works including Boundary wall
Date: January 14 2020
S.n Description of work L, m W,m H,m Area (Sqm. /cum.)
Total Price Deliverables
I Construction of Prefab 6 Bedrooms for 35 Girls Each 20 Sqm.) 1 15.700 7.65 2.75 120 4200071.85 6 Rooms with Door/Window, Light Non-Furnished )
II Construction of Prefab Dinning Hall 1 6 3.25 2.75 20 891735 Hall Room Unfurnished
III Construction of Prefab Kitchen Hall 1 6 3.25 2.75 20 723879 Kitchen with modular Cabinets & Counter Top
IV Construction of Prefab Hall for Reading /TV/ 1 10 4.00 2.75 40 1398800 Hall Room with Unfurnished
V Construction of Prefab Meeting Hall 1 8 3.25 2.75 26 965172 Meeting Hall Unfurnished
VI Construction of Prefab Warden Family House 1 12 4.00 2.75 48 1781856 Family House with Non Furnished
VII Construction of Prefab Common toilet/bathrooms 1 8 3.25 2.75 26 1077076 Toilets with Commode, Tiles, Shower, tap
VIII Construction of Soak pit for Waste and Drain manage 4 2 2.00 1.5 24
cu.m 925000
IX Construction of Water Tank 1 4 2.00 2 12 cu.m 1680000
Sub-total (A) NPR 13,643,589.85
1.2 Installation of Green Solar Plant for Energy Source 2 KW 1 3.00 4.00 NPR 725,300.00 2 Kw solar and 5 lights & System
1.3 Futsal Playground of Size 40 feet x70 fet 1 40.00 10.00 NPR 925,320.00 Futsal Playground
1.4 Compound Work with Metal Pipe & CGI Fencing ( For 2 Ropani Land 1 190 m NPR 1,533,300.00 Metal Fencing with CGI Sheet Cover
1.5 Installation of Water Filter System 1
NPR 455,500.00 Water Filter of 200 liter.
1.6 Installation of Pavement in Ground for 2 Ropani Land (Assumed) 1 100 Sqm NPR 1,150,000.00 Hexagon Pavement in Ground
1.7 Installation of Water Heating Solar for Hot Water Supply 200 l NPR 325,000.00 200l water heating
1.8 Installation of Solar System for Cooking
3 KW( Instead of Bio-Gas) 1 NPR 1,125,000.00 Solar System for Cooking
1.9
Sub-total(B) NPR 6,239,420.00
Total(A+B) NPR 19,883,009.00
VAT 13% NPR 2,584,791.28
Scope of Work Grand Total NPR 22,467,801.13
1 Structure Metal , Prefab Wall , Doors/Window , Roofing False Ceiling ,Painting with turn-key solution
2 25-30 % Advance during MOU
3
Submitted by:
Checked by:
Approved by:
Project Timeline
Address: Dhading
Project :
Starting Date: March First Week
Completion Date:
Project Duration: 5 Months
S.N Works Duration (weeks) Time Period (Week)
3-Mar 25-Mar 5
Apr. 2
May 20
May 2-Jun 25-Jun 2-July 3-
Aug
1 30% Design and Layout 3
2 Site Visit and Custom Fabrication of structure for Project 4
Material for structure and core part delivery 2
3 Structural Metal Frame Installation 3
4 45% Roof Truss and Covering 2
5 Gutter and Flooring PCC 1
6 Ceiling 2
7 Wall Panel installation 3
8 25% Wall Framing Window and Door 2
9 Ground Pavement & Boundary 3
10 Electrification 2
11 Coloring 2
Total Duration : Approx. 5 months including Building Works, Boundary Wall , Ground Pavement
Ref. No:
Master Plan Design and Drawing
Name of Project :- Preparation of Master Plan ,Drawing, Design , Structure Design , Exterior Modeling of Building blocks
Project Summary
SN. Particular Amount Result/ Deliverables
1 Site Survey with Total Station , Surveyor & Assistant team with logistics of team to Dhading (Site Field Visit & Inspection) 32,000.00 Surveyed Map (1:100 Scale)
2 Detailed Concept Planning of Building Block with Placement , Design and Development of Concept in Drawing (2D Autocad) for Real Construction Work by Concept Planner Expert team ( Construction Team , Engineer, Architect) Master Plan Drawing with Beautiful Project placing all blocks in right position and land suitable design and structures with Engineering Safety and Space utilize focused
3 Detailed layout and plan of Septic Tank , Soak Pit ,Water Filter 25,000.00 Drain and Water Filter Placement Layout, Plumbing, Soak Pit Layout Map
4 Master Plan Drawing & Design of Building block ,1 Sport Ground , 1 Vegetable Garden , Solar Panel for Hot Water & Energy for Light , Water Filter System ,2 Ropani Land 75,200.00 Master Plan Including all Blocks in A1 Size Paper
5 Architectural Drawing of 6 Bedrooms Hostel Building (20 sq. m number 6) 38,736.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
6 Architectural Drawing of 1 Dinning Hall 20sq.m 9,684.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
7 Architectural Drawing of Reading Hall 40 Sqm. 19,368.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
8 Architectural Drawing of Meeting Hall 20 sq. m 7,532.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
9 1 Warden Family House Drawing 50 Sqm. 17,216.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
10 2 common bathrooms plus common toilet and hand washing facilities for 35 girls 14,526.00 Arch. Drawing with Elevation , top ,plan view in (A-2 Size)
11 Structural Column Plan , Layout , Truss Details , of All Building Blocks 190,500.00 structural column plan , truss details ,section x-x of Each Block in (A-2 Size), Working Drawing of Building Blocks in A-2
12 Foundation Footing Details & Working Drawing of All Building Blocks 45000.00 Footing Details and Working Drawing of Building in (A-2 ) Size Paper
13 Exterior Model of Building , Landscaping model & Exterior Visualization and Walk through of Complete project Not Required During meeting discussion suggested not required.
14 Bill of Quantity Preparation For Building Blocks 27,000.00 BOQ with Cost For Construction &Material Specification of Structure,Roofing,Wall,Door/Window in details
15 Structure Analysis Report of the Hostel Building >1000 Sqft. 32,550.00 structural report with data analysis and structure recommendations)
16 Electrical & Lighting Placement Drawing 32000.00 Light , Power Socket Drawing in A-2 Size
17 Solar System Installation Modelling and Plan with Details Drawings 30,000.00 Solar Panel Installation Drawing and System Supply Connection Drawing
Subtotal 5961312.00
Total With VAT 13% & 77520.56
Total 673882.56
Note :- Phase #1
Arch. Architectural
COST ESTIMATE FOR Quality Assurance
COST ESTIMATE FOR Quality Assurance
HIRING CONSULTING FIRMS TO CONDUCT FOR Quality Monitoring & Technical Reporting’s During Construction Work and Verifying Work Execution of Prefab Hostel Building with other Necessary Block Project.
S.N Description Person Unit Hr. Rate Total Remark
A Salary of Personnel
2 Architectural Engineer with Construction Supervision 1 14 7500 105,000.00
3 Civil Engineer with Supervision 1 5 5500 27,500.00 .
4 Technical /Structure Engineer Supervision 1 4 16500 66,000.00
Tank, Soak pit, Plumbing , Landscape Supervision 1 5 3500 17,500.00
5 Interior Design, Furniture, Kitchen Designer, Hall Design Consultant 1 5 21500 107500.00
6 ,Electrical Engineer , Sanitary & Waste Manage Expert 1 5 21500 107500.00
A Sub Total 431,000.00
B Miscellaneous expenses
Communication cost 7000.00
Drafting/ reports 20000.00
Equipment’s, vehicles, computers , Software , Analysis 20000.00
Sub Total 47000.00
Grand Total 478000.00
VAT @13% of G 62140.00
Total (G+H) 540,140.00
Building design process
Content
1. Site Survey- Map, Photo, Trace map , Google Map
2. The Concept Plan of the overall project by design team
3. Establishing the need & Requirements with eco-friendly focus.
4. Feasibility Study & Site Survey for the Given Requirement of Building
5. Selection of designers , Structural Engineers as per the job schedules,
6. Drawing and Detailing of Concept design & Planner in AutoCAD and other Software
7. Detailed design –Architectural ,Structural Drawing
8. Production information of Landscape, Ground, Boundary, Building, Draining, Water, Plumbing Works for Construction on-site.
9. Building Model & Structural Design & development with Walk Through
10. Bill of Quantity & Material Specification –
11. Final Cost Estimate Preparation for Construction of Project as per drawing & Design.
12. BID Documents Preparation( If Required)
13. Conclusion ;Find out more & Better Improve
Building’s Construction process
Note: Final Costing and BOQ will be after Preparation of Detailed Project Report( Master Plan, Architectural Drawing , Structural Drawing , Opening Schedules, Foundation Details )
1. Make Booklet Copy with All detailed drawings, master plan, photos.
2. Bid Documents and Get EOI -Comparison
3. Select the Expert and Competitive Firm for Project Execution.
4. Establishing the Scope of Work with the specified Cost for given Work.
5. MoU between Clients and Contractors
6. Start off Project Work with Civil Works,
7. Followed by Foundation, Structure, Wall, Roofing, False Ceiling, Doors/Window Installation / Electrical and Plumbing Works.
8. Quality Assurance by Expert on consulting the work on site specially focused on Architectural Design and Structural Works, Interior Designing, Electrical, Landscape Works.
9. Painting and Finishing Work of Building
10. Production of Futsal, Play Ground, Pavement, Drain – Soak pit, water tank management for Construction on-site.
11. Building Model & Real Construction Comparison and verify and work out best to make everything smooth and fine.
12. Project Summary Reporting and Handover –
13. Find out more & Better Improve
Quality Assurance Process
1. Site Visit and Verify the construction work as per all detailed drawings, master plan, model and photos.
2. Prepare Report and Recommend Contractor for the Work Punch list.
3. Measure, plan and guide for water tank, drain, electrical wiring works.
4. Verifying the Scope of Work and make Clarity between Client and Contractor by the Report of Civil Engineer for given Work.
5. MoU between Clients and Contractors
6. Quality Assurance by Expert on consulting the work on site specially focused on Architectural Design and Structural Works, Interior Designing, Electrical, Landscape Works.
7. Assure Building Safety, Usability and Functionality
8. Guide Worker for Play Ground, Pavement, Drain – Soak pit, water tank management for Construction on-site by Engineer/ Team Leader.
9. Building Model & Real Construction Comparison and verify and work out best to make everything smooth and fine.
10. Project Summary Reporting and Handover –
11. Find out more & Better Improve
Abstract of Cost
Project: Estimate cost of Hostel Building and Prefab Building Block at Dhading , Nepal
Type of work: Construction of Prefab Building Block for Hostel with
Complete works including Boundary wall
Date: January 14 2020
S.n Description of work L, m W,m H,m Area (Sqm. /cum.)
Total Price Deliverables
I Construction of Prefab 6 Bedrooms for 35 Girls Each 20 Sqm.) 1 15.700 7.65 2.75 120 4200071.85 6 Rooms with Door/Window, Light Non-Furnished )
II Construction of Prefab Dinning Hall 1 6 3.25 2.75 20 891735 Hall Room Unfurnished
III Construction of Prefab Kitchen Hall 1 6 3.25 2.75 20 723879 Kitchen with modular Cabinets & Counter Top
IV Construction of Prefab Hall for Reading /TV/ 1 10 4.00 2.75 40 1398800 Hall Room with Unfurnished
V Construction of Prefab Meeting Hall 1 8 3.25 2.75 26 965172 Meeting Hall Unfurnished
VI Construction of Prefab Warden Family House 1 12 4.00 2.75 48 1781856 Family House with Non Furnished
VII Construction of Prefab Common toilet/bathrooms 1 8 3.25 2.75 26 1077076 Toilets with Commode, Tiles, Shower, tap
VIII Construction of Soak pit for Waste and Drain manage 4 2 2.00 1.5 24
cu.m 925000
IX Construction of Water Tank 1 4 2.00 2 12 cu.m 1680000
Sub-total (A) NPR 13,643,589.85
1.2 Installation of Green Solar Plant for Energy Source 2 KW 1 3.00 4.00 NPR 725,300.00 2 Kw solar and 5 lights & System
1.3 Futsal Playground of Size 40 feet x70 fet 1 40.00 10.00 NPR 925,320.00 Futsal Playground
1.4 Compound Work with Metal Pipe & CGI Fencing ( For 2 Ropani Land 1 190 m NPR 1,533,300.00 Metal Fencing with CGI Sheet Cover
1.5 Installation of Water Filter System 1
NPR 455,500.00 Water Filter of 200 liter.
1.6 Installation of Pavement in Ground for 2 Ropani Land (Assumed) 1 100 Sqm NPR 1,150,000.00 Hexagon Pavement in Ground
1.7 Installation of Water Heating Solar for Hot Water Supply 200 l NPR 325,000.00 200l water heating
1.8 Installation of Solar System for Cooking
3 KW( Instead of Bio-Gas) 1 NPR 1,125,000.00 Solar System for Cooking
1.9
Sub-total(B) NPR 6,239,420.00
Total(A+B) NPR 19,883,009.00
VAT 13% NPR 2,584,791.28
Scope of Work Grand Total NPR 22,467,801.13
1 Structure Metal , Prefab Wall , Doors/Window , Roofing False Ceiling ,Painting with turn-key solution
2 25-30 % Advance during MOU
3
Submitted by:
Checked by:
Approved by:
Project Timeline
Address: Dhading
Project :
Starting Date: March First Week
Completion Date:
Project Duration: 5 Months
S.N Works Duration (weeks) Time Period (Week)
3-Mar 25-Mar 5
Apr. 2
May 20
May 2-Jun 25-Jun 2-July 3-
Aug
1 30% Design and Layout 3
2 Site Visit and Custom Fabrication of structure for Project 4
Material for structure and core part delivery 2
3 Structural Metal Frame Installation 3
4 45% Roof Truss and Covering 2
5 Gutter and Flooring PCC 1
6 Ceiling 2
7 Wall Panel installation 3
8 25% Wall Framing Window and Door 2
9 Ground Pavement & Boundary 3
10 Electrification 2
11 Coloring 2
Total Duration : Approx. 5 months including Building Works, Boundary Wall , Ground Pavement